The total length of Tanzania Electric SGR is 2,258.6KM
If you have any question, please ask me.
Status of Dar es Salaam – Morogoro construction (300km) is 98.93%
Tanzania is moving…
Status of Morogoro – Makutupora construction (km 422) is 96.61%
Tanzania is moving…
Dar es Salaam – Morogoro (km 300) 98.93%
Morogoro – Makutupora (km 422) 96.61%
Makutupora – Tabora (km 368) 14.22%
Mwanza – Isaka (km 341) 56.21%
Tabora – Kigoma (Km 506) 1.81%
Uvinza – Musongati – Gitega(Burundi) (km 282) - Financing Process(AfDB)
Can it carry double stack containers like Kenyan diesel SGR?
Dar mpaka mora shi ngapi
Bado LTRA hawajatoa bei. Mwisho wa mwezi wa sita bei zitakuwa zimetolewa
Right now have arrived are wagons for passengers. We expect from July more than 1000 wagons will start entering including double stack container wagons
Tanzania oyeeee!!
Will the height be compatible with the electric lines serving the train?
Yes
Kazi safi Tanzania
Highly doubt this, can you support with technical data
Which Technical Data do you want?
Profile picha yako ni ya usenge