Jubilee Dev - Ongoing construction of 48km long Ngong-Kiserian-Isinya road and 43km long Kajiado-Imaroro road.

The entire project is ahead of schedule with the progress at 57% compared to the time elapsed of 46% and is planned for completion in May 2020. Once completed these roads will ease movement and facilitate economic activity in the areas they traverse.

This is the first road project being implemented under the Annuity Program under which payments to the contractor will be made throughout the life of the project rather than upfront during construction.

This will ensure high-quality construction and proper maintenance of the road throughout its life.
[ATTACH=full]237105[/ATTACH][ATTACH=full]237106[/ATTACH][ATTACH=full]237107[/ATTACH][ATTACH=full]237108[/ATTACH]

Good work.
You should have instead spent that Agenda 4 housing money into opening such infrastructure.

@spear, kuna kabarabara kalikua katoke Igikiro, or something, through Ithanga in Makuyu, to Gatiguru Junction along Garissa road. Apparently, kalianzishwa na president mwenyewe wakati wa kuomba kura in 2016. Je, kamefikia wapi waweza kujua?

can’t wait to hit 200kph hapo

this is the one joining Kenol Mrg road to Kenol- makutano rd?

Rongai-Tuala-Kitengela? what happened?

yaani hii kenia hakuna engineere wanaweza tengeza barabara saffi, lazima iwe foreigners?

Ile yetu ya Kenol-Marua itaanza kujengwa lini?