Jubilee Dev - Construction of 432Km 400kV Loiyangalani-Suswa Line

A section of the 432km 400kV Loiyangalani - Suswa line crossing the Nairobi - Naivasha - Nakuru highway at Karai, Naivasha.
#KETRACOprojects
[ATTACH=full]162093[/ATTACH][ATTACH=full]162094[/ATTACH][ATTACH=full]162096[/ATTACH][ATTACH=full]162097[/ATTACH][ATTACH=full]162098[/ATTACH]

Hii iwekewe kwa portal dunia ione…Jubilee is overworking #MbelePamoja

It’s actually behind schedule and I believe the country is paying heavy penalties for that.

That’s what NMG claimed but on the contract GoK had a force majeure clause to cover it from such unforeseen circumstances. The Spanish company that contracted to do this project went bankrupt. We lost a year going through the steps of picking another contractor. Contrary to speculation LTWP only completed their own installation this year. They were also late. Now they await the completion of this line in Q3.

Bankruptcy does not qualify.

…the reason for bankruptcy