Affordable House

Cost breakdown for a 73 sq m 2 bed 1 bath precast unit with 20 days build time .

  • Precast material (foundation / walling / u-channels ) (Shell structure ) - 580,402
  • Aggregates/Cement/Transport(can vary with location ) - 135,000
  • Precast shell assembly @sh 1000/- per sqm - 70,000/-
  • Skillion roof plus front gutter - 180,000
  • Mettalic windows & doors plus lock - 130,000

Phase one Total cost = 1,095,402
(you can take a pause at this level and prepare for phase two interior finishes )

Phase two :

  • Finishes Exterior cement plaster works Sh 35,000/-
  • Gypsum ceilling - 89,350
  • Interior and exterior Painting works - 135,790
  • Mkeka wa mbao vinyl flooring - 215,000
  • Tiling - 25,000
  • Windows & Doors Glasses - 39,000
  • Plumbing works - 52,000
  • Electricals - 50,000
  • Interior doors and frames - 18,000
  • Worddrobes Cabinets - 70,000
  • Biodigester - 35,000

Total cost Phase 2 = 732,140

Total Amount used to finish the unit labor included = Sh 1,860,542

+++

One wonders why the bother with Kasongo Housing Schemes when one can commit to 17,000/= per month for 10 Years …??? :thinking: